একটা বিল্ডিং এর সকল আইটেম
মিলে ১০০% কিভাবে ভাগ করা হয়। তার সম্ভাব্য নমুনা।
সিভিল, কনস্ট্রাকশন,আর্কিটেক্ট ইঞ্জিনিনিয়ার ভাইদের জানা থাকা জরুরী।
1. Structure
= 35%
2. Brick
work = 6%
3. Wood work
= 5%
4. Metal
work = 2%
5. Plumbing
and Sanitary = 6%
6.
Electrical work = 7%
7. Plaster
work = 4%
8. General
Floor Tiles work = 6%
9. Toilet
& Kit wall Tiles work = 3%
10.
Aluminum work = 4%
11. EME
(Lift, Generator, Substation) = 10%
12. Paint
work = 3%
13. Others
civil work = 6%
14. Utility
connection & Bill = 3%
Total = 100%
STRUCTURE
35%
- Footing
& Column Pedestal = 20%
- Grade
Beam, UGWR top Slab = 5%
- GF Column,
Stair etc. = 4%
- 1st Floor
Slab = 9%
- Typical
Floor Column (5x3%) = 15%
- 2nd floor
slab to roof slab (5x8) = 40%
- Roof top =
7%
TOTAL = 100%
(৩৫% যেভাবে আসবে।)
BRICK WORK
6%
- GF Brick
work = 6%
- 1st floor
Brick work = 18%
- 2nd floor
Brick work = 18%
- 3rd floor
Brick work = 18%
- 4th floor
Brick work = 18%
- 5th floor
Brick work = 18%
-Roof Top
Brick work = 4%
TOTAL = 100%
(৬% যেভাবে হবে।)
WOOD WORK 5%
- Door frame
= 40%
- Main Door
Shutter = 15%
- Partex
Door Shutter = 35%
- Cat Door
& Accessories = 10%
TOTAL = 100%
(৫% যেভাবে হবে।)
METAL WORK
2%
- Window
grill = 55%
- Verandah
Railing = 20%
- Stair
Railing = 10%
- Main gate,
Gen-Sub, safety grill = 15%
TOTAL = 100%
(২% যেভাবে হবে।)
PLAMBING
& SANITARY 6%
- uPVC
vertical line thru duct = 25%
- GI line
work = 30%
- Fixture
& Fittings = 40%
- Ground
Floor = 5%
TOTAL = 100%
(৬% যেভাবে হবে।
ELECTRICAL –
7%
- Conducting
inside slab = 10%
- Conducting
on wall i/c MK box=15%
- Cabling
work = 55%
- Switch-Socket
= 20%
TOTAL = 100%
(৭% যেভাবে হবে।)
PLASTER 4%
- Ceiling
plaster = 20%
- Internal
wall plaster = 50%
- Outside
plaster/facing bricks = 30%
TOTAL = 100%
(৪% যেভাবে হবে।)
GENERAL
FLOOR TILES 6%
- General
floor & Verandah = 75%
- Stair,
typical lobby & lift wall = 20%
- GF lift lobby, wall, reception